What Is Standard Costing? Meaning, Formula, Example And Uses

October 26, 2026 23 min read
On this page
    Summary

    Standard costing means fixing what a unit should cost before you make it, then checking that figure against what you actually spent. The difference is called a variance. Itโ€™s favourable when you spent less, adverse when you spent more. Managers use it to see where materials, labour or overheads ran off plan, and to put someone in charge of fixing it. Standard costing works best in factories that make the same thing again and again. Where every job is different, or where standards never get updated, the numbers stop meaning much.

    Walk into any factory, and youโ€™ll find the same quiet assumption running the show: the next unit should cost roughly what the last one did. Standard costing takes that hunch and pins a number on it, so you can check it later. Below youโ€™ll find standard costing meaning in plain words, the formulas, the types of standards, and one full example where every rupee of variance adds up.

    This guide starts with standard costing meaning in plain words, then moves through the formulas, the types of standards, and standard costing and variance analysis. It ends with one full worked example where every rupee of variance adds up. Short on time? The โ€œAt a glanceโ€ box just below has the quick version.

    Itโ€™s also a topic that separates people who memorise formulas from people who can explain what a variance is telling them. If youโ€™re thinking about a career in management accounting, this is the kind of work the CMA qualification leads to, and the CMA Course is one way in.  

    Google Preferred Sources

    Don’t Let Our Best Advice Get Buried

    Add Imarticus as a Preferred Source — see more of what we publish, every time you search.

    Add Imarticus as a Preferred Source on Google

    What Is Standard Costing?

    Standard costing is a costing method where a business decides in advance what materials, labour and overheads should cost for one unit, then compares that with what it actually spent. The gaps are called variances, and they show where money was saved or lost.

    Thatโ€™s the textbook line. Hereโ€™s the version I actually remember: a railway timetable doesnโ€™t make trains run on time; it just makes lateness impossible to ignore. A standard does that for cost. It wonโ€™t stop material prices rising or a machine jamming. What it does is give you something to measure the damage against. So what is standard costing really asking of you? Predict, write the prediction down before work begins, then admit how far off you were.

    Standard Costing Meaning in Simple Words

    Standard costing meaning, boiled down: decide what a unit should cost, note what it did cost, and ask why theyโ€™re different. CIMAโ€™s official terminology calls it a control technique that reports variances by comparing actual costs with pre-set standards, so action can follow through management by exception. Donโ€™t skim past that last phrase. Nobody can read every number, so you only chase the ones that moved.

    • Need to define standard costing in a line? You fix what a unit should cost before you make it, then compare that with what you really spent.
    • The main features of standard costing: costs fixed in advance, a per-unit view, comparison with actuals, variance reports, and attention only where something moved.
    • Standard cost per unit = standard material + standard labour + standard overhead.
    • Four standards youโ€™ll meet most often: ideal, attainable, basic and current.
    • It works best where one batch looks much like the next.

    If an examiner tells you to define standard costing, your answer needs three things: costs fixed in advance, a comparison with actual costs, and variance analysis for control. Drop any one and the marks go with it.

    Standard Cost vs Standard Costing

    Standard cost is the number. Standard costing is everything around it.

    โ‚น750 a unit is just a figure on a card. Standard costing is the routine of making that card, logging actuals against it every period, working out the gaps and then doing something about them. Ask a student to define standard costing, and plenty will quote a single unit cost, which is the number again, with the system left out.


    Also Read: What does an equity research report include? 


    Standard Costing in Cost Accounting and Management Accounting

    Standard costing in cost accounting is mostly about product costs: stock and cost of goods sold get valued at predetermined figures. Standard costing in management accounting is about control, so it tracks performance, pins responsibility on people and feeds pricing and budgets.

    The two jobs overlap, though they donโ€™t feel the same. On the cost accounting side, life gets easier. Raw materials, work in progress, and finished goods all sit in the books at standard, and the gap between standard and actual goes into separate variance accounts rather than vanishing inside product costs. Thatโ€™s one real difference from budgetary control, where budgets and actuals sit side by side, and the variances never pass through the ledger.

    Management accounting uses those same variances differently, as questions for people. Why did purchasing pay more than planned? Why did the machine shop burn extra hours? A variance nobody owns is just a number on a page, and thatโ€™s usually where these systems quietly die.

    In India, this sits within ICAIโ€™s cost and management accounting coursework and the CMA syllabus. Chapter placement shifts between editions of the study material, so check your current module before planning revision.  


    Did You Know?
    A business may save money by buying cheaper materials, then lose those savings through extra waste or longer production times. Material price and usage variances need to be reviewed together. (Source) 


    Features of Standard Costing

    The features of standard costing are easy to list and just as easy to forget, so each one comes with a reason.

    • Set before production. The standard is a target, not a diary of what happened.
    • Expressed per unit. Quantity and price for materials, hours and rate for labour, an absorption rate for overheads.
    • Compared with actuals every period. Otherwise itโ€™s a guess gathering dust in a file.
    • Variances come labelled. Favourable if actual beat the standard, adverse if it fell short.
    • Management by exception. Only variances outside an agreed tolerance get looked at.
    • Every variance has an owner. Price usually lands with purchasing, usage with production.
    • Built for repeat work. If every job is different, standards donโ€™t mean much.

    Put together, these features of standard costing explain why plants that make the same thing daily love the method, and why workshops that never repeat a job mostly ignore it.

    Objectives of Standard Costing

    The objectives of standard costing stretch past cost control, even though thatโ€™s the one everyone remembers.

    1. Control costs by showing where spending left the plan.
    2. Measure performance of departments, supervisors and lines against a fair yardstick.
    3. Support budgeting. Standards hand you per-unit building blocks.
    4. Simplify costing and stock valuation, since stock carries one agreed figure.
    5. Guide pricing and decisions with a sound view of what a unit ought to cost.
    6. Push cost reduction. Each periodโ€™s variances point at something that could be done better.

    Of all the objectives of standard costing, the one that rarely makes it into notes is a quiet one: it gives a factory a shared number to argue about. Two managers who disagree on whether a process is efficient can at least argue about the same figure.

    Importance of Standard Costing

    The importance of standard costing depends on whoโ€™s asking. Finance gets quicker month-end valuation, production gets a clear target, purchasing gets a price benchmark, and top management gets an early warning.

    Picture what each of them does with it. A finance team valuing stock at standard doesnโ€™t need to retrace the exact cost of every batch. A purchasing manager whose targets are tied to the standard price knows what good looks like before the quarter starts. A plant head reads a variance report on the fifth of the month instead of finding the problem at year-end. None of that is dramatic. Together, it changes how often people look at costs, and how early they spot drift.

    Itโ€™s also the honest answer to why anyone uses standard costing at all. It isnโ€™t accurate (actual costing is more accurate). Itโ€™s useful because you get costs you can act on. The longer list of advantages of standard costing comes later. 


    Also Read: What is the role of financial planning and analysis in a business?    


    Types of Standard Costing

    Most textbooks name four types of standard costing, or strictly four levels at which a standard can be set: ideal, attainable, basic and current.

    TypeWhat it assumesTypical use
    Ideal standardPerfect conditions: no waste, no idle time, no breakdownsStretch targets, continuous improvement drives
    Attainable standardEfficient work, with normal waste and normal downtime allowed forDay-to-day control and budgeting, the most common choice
    Basic standardA fixed base year standard that is not revisedTracking trends over many years
    Current standardConditions as they stand now, valid for a short periodShort-term control when prices or methods are changing

    Some Indian textbooks add a โ€œnormal standardโ€, based on average conditions over a full business cycle. If your exam follows one of those books, use its wording.

    Which type you choose changes how people behave. Set an ideal standard, and youโ€™ll get an adverse variance every single month, until nobody bothers reading the report. Set it too soft, and the variances look lovely while the factory drifts. Most firms land on attainable standards: tough, but not silly.

    Standards by Cost Element

    Whatever the type, a standard is built from three parts. Materials need a quantity and a price. Labour needs hours and a rate. Overheads need a rate per unit of activity, split into variable and fixed.  

    standard costing types

    How to Set Standard Costs

    Setting a standard cost means estimating what materials, labour and overheads should cost per unit, then testing that estimate against history, supplier quotes, time studies and expected volume. Itโ€™s a team job, not just accountingโ€™s.

    1. Gather evidence. Old cost records, supplier quotes, engineering specs, wage agreements.
    2. Pick the standard level. Ideal, attainable, basic or current, and tell everyone which.
    3. Fix quantity and price for materials, with a fair allowance for normal wastage.
    4. Fix hours and rate for labour, using time studies on the operations that matter.
    5. Work out the overhead absorption rate: budgeted overhead divided by budgeted activity.
    6. Write it down, then review it. A standard nobody revises turns into fiction.

    It is wise to keep reminding yourself that every valuation input is an estimate, and standards deserve the same humility. Treat each one as a best guess thatโ€™s probably a little off. The better question isnโ€™t whether the standard was right. Itโ€™s which way it missed, and by how much.

    Standard Cost Card

    Hereโ€™s the card weโ€™ll use in the worked example. The numbers are hypothetical.

    ElementStandardCost per unit
    Direct material2 kg at โ‚น150 per kgโ‚น300
    Direct labour3 hours at โ‚น100 per hourโ‚น300
    Variable overhead3 labour hours at โ‚น40 per hourโ‚น120
    Fixed overheadโ‚น1,20,000 budgeted รท 4,000 budgeted unitsโ‚น30
    Standard cost per unitโ‚น750
    standard costing steps

    Standard Costing Formula

    The standard costing formula, in its simplest form, is: standard cost per unit = standard material cost + standard labour cost + standard overhead cost. Everything else, variances included, grows out of that one line.

    • Standard material cost = standard quantity ร— standard price
    • Standard labour cost = standard hours ร— standard rate
    • Standard overhead rate = budgeted overhead รท budgeted activity
    • Standard cost of actual output = standard cost per unit ร— actual units produced

    That last line is where students slip. Variances are measured against the standard cost of the units you actually made, not the units you planned. Budget 4,000, make 3,800, and the standard quantity of material is worked out for 3,800. The variance formulas below use (standard โˆ’ actual), so a positive answer is favourable, and a negative one is adverse.

    VarianceFormula
    Material price(Standard price โˆ’ Actual price) ร— Actual quantity
    Material usage(Standard quantity for actual output โˆ’ Actual quantity) ร— Standard price
    Labour rate(Standard rate โˆ’ Actual rate) ร— Actual hours
    Labour efficiency(Standard hours for actual output โˆ’ Actual hours) ร— Standard rate
    Variable overhead expenditure(Actual hours ร— Standard variable rate) โˆ’ Actual variable overhead
    Variable overhead efficiency(Standard hours for actual output โˆ’ Actual hours) ร— Standard variable rate
    Fixed overhead expenditureBudgeted fixed overhead โˆ’ Actual fixed overhead
    Fixed overhead volume(Actual output โˆ’ Budgeted output) ร— Standard fixed overhead per unit

    Pro Tip: When calculating variances, use the standard quantity and hours allowed for the output you actually produced. Comparing actual costs with the original production budget can distort the result when output changes.


    Standard Costing and Variance Analysis

    Standard costing and variance analysis canโ€™t really be pulled apart. The standard is the question, the variance is the answer, and analysis is figuring out what that answer means. Each of the variances tells you something different, so donโ€™t read them in isolation.

    Material Variances

    Keep them apart, because different people are responsible. Purchasing can post a nice favourable price variance by buying cheaper stock, then cause an adverse usage variance the same month because that stock wastes more on the line. 

    • Price variance: did you pay more or less than planned?
    • Usage variance: did you use more or less than the standard allows?

    Only the two together show what happened.

    Labour Variances

    The rate variance compares the wage actually paid with the standard rate. The efficiency variance compares hours worked with the hours the output should have taken. Use a more experienced worker, and you may see an adverse rate variance with a favourable efficiency variance. Whether thatโ€™s a good deal depends on the total, not on either figure alone.

    Overhead Variances

    Variable overhead splits into expenditure and efficiency, same as labour. Fixed overhead is the odd one out. Its expenditure variance tells you whether you overspent the budget, but its volume variance is really about whether the plant was busy. When a plant makes fewer units than budgeted, the fixed overhead volume variance goes adverse even if nobody overspent a rupee. Read it as a comment on capacity, not spending.

    Favourable Is Not Always Good

    A favourable variance is just a gap in the nice direction. It could be a genuine saving. It could also be cheap material that fails inspection later, or a standard set too loose. Find out where it came from before anyone celebrates.

    Who Investigates What

    This is where standard costing meets responsibility accounting: each variance should land on the desk of whoever controls its cause.

    VarianceCommon causesUsual owner
    Material priceSupplier changes, rush buying, order sizePurchasing
    Material usageWastage, poor quality input, machine settingsProduction
    Labour rateOvertime, skill mix, wage changesProduction or HR
    Labour efficiencyTraining, idle time, machine breakdownsProduction
    Variable overheadPower and consumables usage, spending controlDepartment heads
    Fixed overhead volumeDemand shortfall, capacity planningManagement

    Management by exception finishes the job. Set a tolerance, say investigating only variances above an agreed percentage of standard, and let everything inside the band go. Without that, the report is a wall of numbers nobody reads. 


    Did You Know?
    An ideal standard assumes perfect conditions, with no defects, waste or machine breakdowns. An attainable standard allows for normal operating issues and can provide a more realistic performance target. (Source) 


    Standard Costing Example With Solution

    This is the sort of question that turns up in standard costing in cost accounting papers, so go through it slowly. The figures are hypothetical.

    Question. A company budgets for 4,000 units. The standard cost card is the one above: 2 kg of material at โ‚น150, 3 labour hours at โ‚น100, variable overhead at โ‚น40 per labour hour, and a fixed overhead budget of โ‚น1,20,000. In the period, it makes 3,800 units. It buys and uses 7,900 kg at โ‚น155 per kg, works 11,600 hours at โ‚น104 per hour, and incurs variable overhead of โ‚น4,75,000 and fixed overhead of โ‚น1,26,000. Calculate the variances.

    Step 1: Standard cost of actual output. 3,800 units ร— โ‚น750 = โ‚น28,50,000. The standard quantity for 3,800 units is 7,600 kg, and the standard hours are 11,400.

    Step 2: Actual cost. Material 7,900 ร— 155 = โ‚น12,24,500. Labour 11,600 ร— 104 = โ‚น12,06,400. Variable overhead: โ‚น4,75,000. Fixed overhead: โ‚น1,26,000. Total โ‚น30,31,900.

    Step 3: Variances.

    VarianceWorkingAmount
    Material price(150 โˆ’ 155) ร— 7,900โ‚น39,500 adverse
    Material usage(7,600 โˆ’ 7,900) ร— 150โ‚น45,000 adverse
    Labour rate(100 โˆ’ 104) ร— 11,600โ‚น46,400 adverse
    Labour efficiency(11,400 โˆ’ 11,600) ร— 100โ‚น20,000 adverse
    Variable overhead expenditure(11,600 ร— 40) โˆ’ 4,75,000โ‚น11,000 adverse
    Variable overhead efficiency(11,400 โˆ’ 11,600) ร— 40โ‚น8,000 adverse
    Fixed overhead expenditure1,20,000 โˆ’ 1,26,000โ‚น6,000 adverse
    Fixed overhead volume(3,800 โˆ’ 4,000) ร— 30โ‚น6,000 adverse

    Step 4: Reconcile. Material cost variance is โ‚น84,500, labour โ‚น66,400, variable overhead โ‚น19,000 and fixed overhead โ‚น12,000. Together thatโ€™s โ‚น1,81,900, exactly the gap between actual cost (โ‚น30,31,900) and standard cost (โ‚น28,50,000). If yours donโ€™t land there, a working is wrong somewhere. This check catches it every time.

    What the numbers say. Every variance is adverse here. Youโ€™d rarely see that in a real plant, but itโ€™s handy for teaching. The numbers donโ€™t tell you why, only where to ask. Material usage is the biggest single figure, so Iโ€™d begin there, production first and purchasing second, since the two material variances may be linked.

    Want to practise? Try these.

    1. Standard: 5 kg at โ‚น20 per unit. Actual: 1,000 units made, 5,200 kg bought and used at โ‚น19. Find the material price and usage variances. (Price โ‚น5,200 favourable, usage โ‚น4,000 adverse.)
    2. Standard: 2 hours at โ‚น50 per unit. Actual: 500 units made, 1,100 hours at โ‚น52. Find the labour rate and efficiency variances. (Rate โ‚น2,200 adverse, efficiency โ‚น5,000 adverse.)
    3. Budgeted fixed overhead โ‚น60,000 for 3,000 units. Actual output 2,700 units, actual fixed overhead โ‚น58,000. Find the expenditure and volume variances. (Expenditure โ‚น2,000 favourable, volume โ‚น6,000 adverse.)

    If working through this feels like something youโ€™d happily do every week and not just before an exam, thatโ€™s a decent sign.  


    Pro Tip: Check material price and usage variances side by side. A lower purchase price may come with higher waste. The combined picture gives managers a better basis for action.


    Difference Between Standard Costing and Budgetary Control

    The difference between standard costing and budgetary control is mostly scope. Budgetary control plans and controls the whole business. Standard costing controls the cost of one unit of product or service.

    Budgets tell you what you can spend. Standards tell you what a unit ought to cost. Both start from the same instinct (set a target, measure the result, find the gap, act on it) and in practice they feed each other.

    PointStandard costingBudgetary control
    ScopeProduct or service, cost element by cost elementWhole department or business, including sales, capital and finance
    NatureIntensive, concerned with unit costExtensive, concerned with totals
    RecordingActuals recorded in the accounts and variances revealed through variance accountsBudgets and actuals compared side by side, variances not shown in the accounts
    Partial useNot really possible; it needs the full systemPossible, for example a cash budget or a selling expense budget alone
    PolicyCan be used without a stated business policyNeeds a clear policy or objective for the period
    TargetA yardstick of what cost should beA ceiling on what may be spent

    Standard Costing vs Actual, Absorption and Marginal Costing

    These arenโ€™t all rivals. Standard costing and actual costing differ in which figures you use. Absorption and marginal costing differ in which costs go into a product. So you can run standard absorption costing or standard marginal costing, and the two choices are independent.

    The difference between standard costing and budgetary control is not the same as the difference between standard costing and absorption costing, and mixing them up is a classic exam slip.

    MethodWhat goes into product costBest suited to
    Actual costingActual materials, labour and overhead as incurredCustom or one-off jobs
    Normal costingActual materials and labour, overhead at a predetermined ratePlants with stable overheads but changing input costs
    Standard costingPredetermined material, labour and overhead standardsRepetitive production with stable processes
    Absorption costingVariable and fixed manufacturing costsExternal reporting
    Marginal costingVariable costs onlyDecisions on pricing and product mix

    Standard Cost vs COGS

    Standard cost is what a unit should cost. Cost of goods sold is what the units you sold actually cost, once variances are accounted for. If stock is valued at standard, COGS starts at standard too, and the variances are either written off to the period or spread across stock and COGS, depending on policy. 


    Also Read: What are the most common capital budgeting examples?  


    Advantages of Standard Costing

    The importance of standard costing shows up as one habit: cost control stops being a year-end review and becomes a monthly routine.

    • Cost control. Problems show up while theyโ€™re still small.
    • Better budgets. Per-unit standards make planning quicker and less of a guess.
    • Fairer performance checks. People are judged against a stated target, not against each other.
    • Simpler stock valuation. One agreed value for the period.
    • Faster reports. Management by exception means less to read.
    • Sharper pricing. Sales can see the margin before quoting.
    • Cost awareness. People who know the target tend to waste less.

    Limitations of Standard Costing

    The limitations of standard costing are real, and a decent notes page should say so. The method was built for stable, repetitive factories, and in plenty of places business has moved on.

    • Outdated standards. Standards go stale quickly, nobody enjoys revising them, and reports built on old standards mislead.
    • Poor fit for custom work. If every job differs, setting standards costs more than it saves.
    • Behavioural side effects. Supervisors may put off maintenance to protect a labour efficiency figure, or push output just to avoid a volume variance.
    • Time lag. You only learn the variances after the period closes, which can be too late.
    • Quality and speed stay invisible. A cost standard says nothing about customer satisfaction or innovation.
    • Setup and upkeep. Small firms may not have the people to keep it running.

    How to Reduce These Limitations?

    Use attainable standards, not ideal ones. Revise when input prices or methods change in a big way, not just once a year. Put quality and delivery measures next to the variance reports. And apply standards to the repetitive parts of a process even when the whole output isnโ€™t standardised.

    Where Standard Costing Is Used?

    Standard costing in management accounting is most at home in manufacturing with repeatable processes: food, chemicals, consumer goods, auto components. It works in services too, wherever thereโ€™s a measurable unit, like a processed insurance claim or a cleared cheque.

    How to Check Standard Costing in SAP?

    In SAP, standard costing runs on the price control indicator. A material set to โ€œSโ€ in the accounting view of the material master is valued at a standard price. That price comes from a cost estimate, usually created with transaction CK11N and released through CK24. To simply view the current standard price, the accounting view in MM03 shows it. Transaction codes can differ by version, so confirm with your SAP team.  


      Choosing the CMA path calls for a clear view of the costs, career opportunities, earning potential and skills the qualification can bring. Weighing these factors can help you decide how well the certification fits your long-term goals in management accounting and finance.


    Build Practical Cost Management Skills With Imarticus Learning’s US CMA Course

    If this topic made you want to work with costing and variances every day, the CMA is where it goes deeper. Hereโ€™s what the CMA Course by Imarticus Learning offers: Standard costing gives you a foundation in cost control and variance analysis. The US CMA course takes these skills further into budgeting, performance management and business decision-making. Imarticus Learning combines exam preparation with practical business applications to help you connect accounting concepts with workplace needs.

    • 6 to 8 months of training, with online live and offline classroom options.
    • Faculty holding US CMA, US CPA, CA and CFA credentials.
    • KPMG in India collaboration: 12 one-hour live sessions a year led by practitioners, and business case studies they evaluate.
    • Surgent review content, and Imarticus is an IMA Gold Learning Partner.
    • iLeap learning platform with timed mock tests, a custom quiz builder and a 24/7 AI doubt solver.
    • Mentoring: one-to-one on the online plan, group sessions on the offline plan.
    • 50% money-back guarantee if you complete the classes, attempt the exams and donโ€™t pass.

    FAQs About Standard Costing

    From tricky variance calculations to choosing the right cost standard, get clear answers to the most frequently asked questions that often arise when applying standard costing in exams and real business situations. 

    What are the four types of standard costing?

    The four types of standard costing include: deal, attainable, basic and current. Ideal assumes perfect conditions, attainable allows for normal waste and downtime, basic is a fixed base year standard, and current reflects present conditions. Most firms use attainable standards for control.

    How do you calculate standard cost?

    To calculate standard costing, multiply standard quantity by standard price for materials, standard hours by standard rate for labour, then add an overhead rate per unit. Add the three and you have the standard cost per unit.

    What is the difference between standard costing and COGS?

    Standard cost is a planned cost per unit. COGS is what the goods sold actually cost. In a standard system, COGS starts at the standard and gets adjusted for variances.

    What is standard costing with an example?

    An example of standard costing would be: say a unit should use 2 kg of material at โ‚น150, 3 labour hours at โ‚น100 and overheads of โ‚น150. Its standard cost is โ‚น750. At period end, you compare actual cost with that figure to find the variances.

    Why use standard costing?

    Standard costing makes cost control routine. Managers see variances early, budgets get easier to build, and stock is valued consistently. The advantages of standard costing are strongest in repetitive production.

    What is the formula for standard costing?

    The standard costing formula is: standard cost per unit = standard material + standard labour + standard overhead. Each part is quantity or hours times price or rate, and overhead uses a predetermined absorption rate.

    How to check standard costing in SAP?

    To check standard costing in SAP, heck that the price control indicator on the material master is set to โ€œSโ€. The current standard price shows in the accounting view, and cost estimates are handled through CK11N and CK24.

    What are the disadvantages of standard costing?

    The disadvantages of standard costing would be that it can go out of date, doesnโ€™t suit custom work, can nudge people into odd behaviour and reports variances late. The limitations of standard costing are manageable if standards are revised often and read alongside quality measures.ย 


    From Standard Costing Theory to Real Decisions 

    Standard costing meaning fits in one breath: decide what a unit should cost, measure what it did cost, and chase the difference. The formulas, the types of standards and the eight variances in this guide are that loop, done carefully.

    If you keep only three things, keep these. Set attainable standards. Ideal ones produce adverse variances every month, until nobody reads the report. Reconcile every time. If your variances donโ€™t add up to the gap between actual and standard cost, a working is wrong. Give each variance an owner. A number nobody owns changes nothing.

    The part Iโ€™d stress most is that standard costing is a way to ask better questions, not to hand out blame. A variance tells you where to look. It rarely tells you why. For an exam, the formulas will get you through. For a career, the real skill is explaining a gap so people act on it, and thatโ€™s what standard costing in management accounting trains. If youโ€™d like guided practice and mentoring while you build it, the Imarticus Learning CMA Course is one route worth a look. Either way, rework the example above once on paper, without peeking.

    Liked This? Follow Us Where You Already Search.

    Preferred Sources is Google’s built-in follow button — no app, no login, just more Imarticus in your results.

    Add Imarticus as a Preferred Source on Google
    Prabodh Nayak
    Written by

    Prabodh Nayak

    Senior Faculty, Imarticus Learning

    Prabodh (US CMA, ACCA, CPA, CFA, FRM, BA), is a senior finance professional with expertise in Strategic Planning, Financial Reporting, Costing, Finance, Taxation (UK & US), and Business Analytics. He comes from a very diversified and credible academic background of CA, US CMA, US CPA & CFA. He has an overall industry experience of more than 2 decades & worked with KPMG in past. For more than a decade he has been teaching US CMA, ACCA, CFA, US CPA, FRM & Business Analytics courses and is one of the most seasoned finance trainers in the country.